CONTINUING problems with the footbridge across Peel harbour mean that it will be out of action for six weeks from this Sunday for major repairs.
The Department of Infrastructure has revealed today that the bridge - known as the Fenella Footbridge - will have to be lifted for “essential repairs and maintenance” from Monday 7th March until Thursday 21st April 2011.
Problems with the bridge were first noticed in early 2009 when the main slewing bearing assembly failed. The bndge was closed in May 2009 and a temporary repair made it possible to continue at a reduced and controlled frequency.
However, the bearing failed again in June 2010. resulting in the Department commissioning an independent investigation into the circumstances of the failure and invited recommendations in relation to a permanent and robust repair.
Recommendations have been received for a permanent repair and those recommendations have been accepted by the Department.
David Callister, MLC, Member for Harbours, said, “It is very regrettable that there have been problems with the bridge; however this work will correct the problems.
“The planned repair will require the bridge to be lifted on to the adjacent quay to enable the slewing mechanism to be removed and modified. Whilst this work is underway and without any additional delay the opportunity will be taken to maintain the main structure of the bridge as part of our normal scheduled maintenance programme. To enable this work a site will be fenced off on the East Quay Pier.”
Additionally, whilst the cranes are on site, necessary inspection and minor maintenance work will be undertaken on the flap gate. This work will be carried out, weather permitting, between high water (1240hrs) on Tuesday 8th and high water (1416hrs) on Thursday 10th March.
The work will involve putting in place two large steel barriers, on one side of the gate by crane to create a safe working environment. During the time that they are in place it will not be possible for vessels to enter or leave the inner harbour.
Harbour operations will not be affected by the removal of the bridge although there will be inconvenience to pedestrians. There will be an impact on the harbour due to the inspection of the flap gate but this will be kept to a minimum.
A spokesman said, “The Department apologises for inconvenience caused to harbour users and the general public during in this essential work and will make every effort to have the bridge back in service in time for Easter.”