First phase of Prom upgrade will take time - but be top quality

by isleofman.com 9th July 2013
The Director of Highways says the first phase of work to give Douglas Promenade a massive facelift should be completed by next TT.
During its sitting this week, Infrastructure Minister David Cretney will ask Tynwald for ?1.6 million for improvements between the Sea Terminal and the Jubilee Clock.
That phase of the enormous project should take just over nine months to complete.
Richard Pearson says there’s a reason so much time and effort will be spent on a relatively short stretch of road:
Clip 1
Posted by isleofman.com
Tuesday 9th, July 2013 09:47pm.

Popular Articles

Upcoming Events

Bridge Club

Monday is Bridge Day at the Onchan Pensioner's Social Club   We have two bridge clubs that meet on a weekly...
23 Jun

Nobles Parkrun

A free, fun, and friendly weekly 5k community event in Nobles Park.  Walk, jog, run, volunteer or spectate...
28 Jun
View More
Advertisement

You also might be interested in

Stephen Savage joins Quinn Legal’s Corporate and Commercial legal team.

Business

When the clocks sprung forward we lost another precious hour of sleep

Health & Wellness

The GFoGE guide to obstacle races & why should you do one.

Sports & Leisure

Why not take a "Wallaby" walk in the Curragh?

Nature & Wildlife

Hop-tu-Naa is an ancient festival celebrated on the Isle of Man

Visitor Guide

The Isle of Man hosts many traditional ceremonies throughout the year

Visitor Guide