Ramsey Sprint - but only walkers for swingbridge

by isleofman.com 28th May 2014
Work on the Ramsey swing bridge is going well - but it's not going to be open in time for the Ramsey Sprint next Tuesday.
So says the Department of Infrastructure which reported in February that 20 iron wheels within the bridge mechanism were an inch undersized and needed to be re-engineered.
It had originally been hoped the bridge would be open in time for TT, but this delay put the work back. Residents have expressed concern that there will only be limited pedestrian use during one of the busiest days of the year in the town.
It's hoped to make up time on the scheme after TT by combining the remaining engineering work with painting the structure.
But Director of Ports, Anne Reynolds, says it does mean only very limited use of the bridge will be possible during the Sprint
Clip 1
Posted by isleofman.com
Wednesday 28th, May 2014 12:40pm.

Popular Articles

Upcoming Events

Nobles Parkrun

A free, fun, and friendly weekly 5k community event in Nobles Park.  Walk, jog, run, volunteer or spectate...
10 May

Bridge Club

Monday is Bridge Day at the Onchan Pensioner's Social Club   We have two bridge clubs that meet on a weekly...
12 May
View More
Advertisement

You also might be interested in

Stephen Savage joins Quinn Legal’s Corporate and Commercial legal team.

Business

When the clocks sprung forward we lost another precious hour of sleep

Health & Wellness

The GFoGE guide to obstacle races & why should you do one.

Sports & Leisure

Why not take a "Wallaby" walk in the Curragh?

Nature & Wildlife

Hop-tu-Naa is an ancient festival celebrated on the Isle of Man

Visitor Guide

The Isle of Man hosts many traditional ceremonies throughout the year

Visitor Guide